A public update meeting for the Piqua Dam Removal and Modification Project will take place on Monday, September 16 at 5:30 pm in the Commission Chambers, located on the second floor of the Municipal Government Complex, 201 W. Water Street, Piqua, OH 45356.
At the meeting, FlatLand Resources and Ecosystem Services will provide an update on the project progress, present the 30% design plans (which include the proposed in-stream and river corridor improvements), and discuss the anticipated construction timeline. Following a short presentation, there will be an opportunity for attendees to ask questions and comment on the project plans.